Have Four years of professional experience in Electrical Testing & Commissioning with a proven ability to achieve and exceed all Technology development and Power-generational goals of the company.
ACADEMIC QUALIFICATIONS :
** B.E - Electrical and Electronics Engineering from Erode Sengunthar Engineering College, Erode. With 68.4 % in2016.
** XII class from VNUP Kaleeswari Higher Secondary School, Vanniampatty. With 74.4% in2012.
** X Class from VNUP Kaleeswari Higher Secondary School,Vanniampatty. With 87.7% in2010.
PRESENT EMPLOYER :
Organization : M/s. VOLTECH ENGINEERS PVT. LTD
Designation : Senior Commissioning Engineer.
Duration : MAY 2016 to tilldate
KEY PROJECT HANDLED :
Achievements :
ØGot best performer of the year 2018-2019 award from voltech group of companies at 24 th anniversary.
Testing kit handled :
** CTanalyzer(omicron)
** CPC80(omicron)
** Transformer winding resistance kit(scopemake)
** CRM (scopemake)
** Turns ratio kit (ELTELmake)
** CT,CVT measuringkit
** Basic testing equipmentsused.
** Single phase relay kit secondary injection.
** 60-70 HV kit.
Present Project : 1*660MW TPS SubStation,UPRVUNL ,TOSHIBA JSW plant (Uttarpradesh )
Client : M/s ABB INDIA LIMITED.
Testing and commissioning of full switchyard including scheme checking and interlock checkings at 660MW thermal power plant unit with GTCommissioning.
Project : 132kv/11kv/3.3kv – AIS SubStation,ESSAR plant (vishakapatnam ) Client: M/s ABB INDIA LIMITED.
** Testing of CT, PT, and Breaker, isolator in 132KV, 11KV &3.3KV.
** CT testing with CT analyzer omicronkit.
** Testing and commissioning of ABB PASSequipment.
** Testing of Earth pit resistance and Surgecounter.
** Hipot Testing of 11kvcables.
** Testing ofREF615.
** 11kv auto changeover schemechecked.
** Testing of 20 MVA Power Transformer with all Protection check (Bucholz, OTI, WTI,OSR andPRV).
** Commissioning of 132 KV Relay and control & RTCCpanels.
** ABB Scheme checksdone.
** Transformer stability and REF stabiltydone.
** Substation chargedsuccessfully.
Project : 765/400kv AIS Power Grid Corporation of India Ltd (PGCIL, ODISHA) Client: M/s TECHNO ELECTRIC & ENGINEERS PVT LTD.
** Testing and Commissioning of CT,PT and Breaker ,Isolator in 765 &400KV.
** Testing of Earth pit resistance and Surgecounter.
** Commissioning and Interlock checking of 765 & 400kv CRP,PLCCPanels.
Project : 400kv GIS Power Grid Corporation of India Ltd (PGCIL, ODISHA) Client: M/s TECHNO ELECTRIC & ENGINEERS PVT LTD.
** Testing and Commissioning of CT,PT,and Breaker,Isolator in 765 &400KV.
** Commissioning and Interlock checking of 765 & 400kv CRP,PLCCPanels.
** SIEMENS Scheme checksdone.
Project : 220/132/33KV AIS Odisha power transmission corporation of limited(BALASOOR,ODISHA)
Client : M/s Gupta power Infrastructure Limited, Odhisa.
** Testing and Commissioning of 160 MVA Auto Transformer with all Protection check (Bucholz, OTI, WTI, OSR andPRV).
** Commissioning of 220kv &132kv CRP and RTCCpanel.
Project : 33/0.433 kV AIS substation, UTKAL ALUMINA PLANT (Tikiri, ODISHA) Client: M/s Sunray Electricals Limited, Odhisa.
** Testing & Commissioning of 5 MVA Transformers 4nos.
** Transformers Differential Stability, REF andStability.
** Testing & commissioning of 33 and 0.433 kV Electrical Equipments CT, PT, Breaker, Cable, Busbar, Isolators, Earth switches and Interlockstroughed.
** Commissioning of 33 kV AUTO CHANGE OVER Schemechecked.
** Testing & Commissioning of 415V Panels ACDB,MLDB.
** Testing & Commissioning of 110V PanelsDCDB.
** L&T Scheme checksdone.
** Substation chargedsuccessfully.
Project : 765/400kV AIS substation,Power Grid Corporation of India Ltd (PGCIL, chattisgarh.)
Client : M/s TECHNO ELECTRIC & ENGINEERS PVT LTD.
** Pre-commissioningactivities.
** Protection and operationchecking.
** Scheme checking and substationcharging.
** Testing of CT with CT analyzer omicronkit.
** Testing of Earth pit resistance and Surgecounter.
** Testing and commissioning of 400kvReactor.
** Schneider Scheme checksdone.
** Busbar stabilitydone.
** Substation chargedsuccessfully..
Project : 11/6.6/0.433kV SubStation Bokaro steel plant (JHARKANT) Client: M/s S.P Enterprises.
** Testing & Commissioning of HT ,LT, PMCC, and MCC Panel with allEquipment’s.
** Testing & Commissioning of 5.5 MVA autotransformer.
** Testing of Earth pit resistance and Surgecounter.
** Pre-commissioningactivities.
** Protection and operationchecking
** Scheme checking and substationcharging.
** Transformers Differential Stability, REF and Stabilitydone.
** Substation chargedsuccessfully.
Project : 400kv AIS, substation Power Grid Corporation of India Ltd (PGCIL, ODISHA.) Client: M/s SR Associates,Bhubaneswar.
** Testing & commissioning of 400kv Electrical Equipment CT, PT,Breaker.
** Testing of CT with CT analyzer omicronkit.
** Testing of Earth pit resistance and Surgecounter.
** Commissioning of 400kv CRP&PLCCpanel.
** Protection tripping and Alarmchecked.
Project : 400kv AIS, substation Power Grid Corporation of India Ltd (PGCIL, BIHAR.) Client: M/s Empower
** Testing & Commissioning 400 kv LINE bay with local and remote operations checking of equipments.
** Commissioning of 400kv CRP&PLCCpanel.
** Signal testing done from relay toSCADA.
** Bus bar stabilitydone
** AREVA Scheme checks done.
** Substation chargedsuccessfully.
Project : 33kV/0.433V switchgear SubStation, (NAYA RAIPUR ) Client: M/s JMC Limited, NAYA RAIPUR.
** Testing & Commissioning of 33 kV Electrical Equipment Testing of CT, PT, Breaker, CT Chamber, Cables, Bus barsdone.
** Testing of HT, PCC, MCC Panel with all Equipment’s including ACB and Micom P111 Relay.
** Testing of APFCpanel.
** Testing & Commissioning of 415V ACDB Panels 10 KVA ControlTransformer.
** Testing & Commissioning of 110V PanelsDCDB.
** Commissioning of HT,PCC, MCC Panelsdone.
Project : 6.6kV/0.433V switchgear SubStation, ( PARADIP ) Client: M/s IFFCO Limited, odisha.
** Testing & Commissioning of 6.6 kV Electrical Equipment Testing of CT, PT, Breaker, CT Chamber, Cables, Bus barsdone.
** Testing of HT, PCC, MCC Panel with all Equipment’s including ACB and Micom P111 Relay,micom o/v,u/vrealy.
** Testing & Commissioning of 415V ACDB Panels 10 KVA ControlTransformer.
** Testing & Commissioning of 110V PanelsDCDB.
** Commissioning of HT,PCC, MCC Panelsdone.
** Siemens scheme checksdone.
Project : 33kV/0.433V switchgear at medical college.
( PARIPADA ) Client: M/s Star Delta electricals Limited, odisha.
HIPOT Testing of cables and Lightningarrester.
Project : 220/132/33KV AIS Bihar State power transmission corporation of limited(kishanganj,Bihar)
Client : M/s TECHNO ELECTRIC & ENGINEERS PVT LTD.
** Testing and Commissioning of 50 MVA power Transformer with all Protection check (Bucholz, OTI, WTI, OSR andPRV).
** Commissioning of 1320kv CRP and RTCCpanel.
** CGL Scheme checksdone.
** Transformer stability and REF stabiltydone.
Project : 220/132/33KV AIS Bihar State power transmission corporation of limited(Lukhahi,Bihar)
Client : M/s TECHNO ELECTRIC & ENGINEERS PVT LTD.
** Testing and Commissioning o 2 extension future linebay.
** Commissioning of 220kvCRP.
** CGL Scheme checksdone.
** Bus bar stabilitydone.
** Substation Charged successfully
Project : 400kv AIS, substation Power Grid Corporation of India Ltd (PGCIL, BIHAR.) Client: M/s sterling and wilson
** Testing & Commissioning 400 kv LINE bay with local and remote operations checking of equipments.
** Commissioning of 400kv CRP&PLCCpanel.
** Signal testing done from relay toSCADA.
** Bus bar stabilitydone.
** Reactor testing with stabilitydone.
** Alstom Scheme checksdone.
** Substation chargedsuccessfully.
Project : 3.3/0.433kv, substation at ITC ltd (West Bengal , Tribeni.) Client: M/s SIEMENS LTD
** Commissioning 3.3/0.433 kv Feeder with capacitorbank.
** Trouble shooting of APFC Panel trippingissues.
Project : 400kv AIS, substation Bus reactor BAY Power Grid Corporation of India Ltd (PGCIL, ASSAM.)
Client : M/s sterling and wilson
** Testing & Commissioning 400 kv Bus reactor 125 Mvar bay with local andremote operations checking ofequipments.
** Commissioning of 400kv CRPpanel.
** Signal testing done from relay toSCADA.
** Bus bar stabilitydone.
** Reactor testing with stabilitydone.
** Alstom Scheme checks done. Substation chargedsuccessfully
Project : 13.8/400kv GIS 4*180 MW Hydro power plant, Bhutan power transmission limited,(MHPA, BHUTAN.)
Client : M/s BHEL
** Testing & Commissioning 400 KV BAYS with local and remote operations checkingof Equipments.
** Commissioning of 400kv WITH SELL RELAY CRPpanel.
** Signal testing done from relay toSCADA.
** Testing of Excitation transformers and auxiliarytransformers.
** BHEL Scheme checksdone.
KEY SKILLS :
** Excellent safety health and environment managementskills
** Excellent planning & contingency managementskills.
** Excellent Co-ordination for team work & good team player.
** Excellent communication skills -Contacting various user groups, discussing project requirements, Development and discussing testplans.
** Knowledge in Windows products likes , MS-Word, MS Power Point,Excel.
** Basics with PLC,scada,C,C++.
** Basics with ORCAD,
PERSONAL INFORMATION :
Father Name : SUNDARAM.K
Date of Birth : 26th MAY1995
Nationality :Indian
LanguagesKnown : English, Tamil &Hindi.
DECLARATION :
I hereby declare that all the particulars furnished in this resume are true, correct and complete to the best of my knowledge and belief.
PLACE :
DATE :